Notice of General Meeting

A General Meeting of the Company will be held at the Conference Room, Ground Floor, BGC Centre, 28 The Esplanade, Perth, Western Australia on Friday 18 May 2018 commencing at 10:00am (WST).

This Notice and the accompanying Explanatory Memorandum should be read in its entirety. If Shareholders are in doubt as to how they should vote, they should seek advice from their stock broker, investment advisor, accountant, solicitor or other professional adviser prior to voting.

Should you wish to discuss any matter please do not hesitate to contact the Company Secretary by telephone on + 61 8 9322 6322.

Shareholders are urged to attend or vote by lodging the Proxy Form attached to the Notice.

Piedmont Announces Positive Initial Metallurgical Results and Sets Development Timeline

NEW YORK, April 9, 2018 /PRNewswire/ —

  • Piedmont has established a large land position in the historic lithium region of North Carolina, USA
  • Aggressive drilling continues to define high grade mineralisation supporting the completion of a maiden Mineral Resource by the end of Q2 2018
  • Piedmont has commenced an integrated Scoping Study with completion expected in Q3 2018
  • Initial spodumene flotation test work indicates spodumene concentrate grades exceeding 6.0% Li2O and less than 1.0% Fe2O3
  • Baseline permitting work is underway and permit applications are on track for submittal in Q4 2018
  • The Scoping Study will highlight the positive economic implications of Piedmont’s unique location, which are evident in benchmarking key capital and operating cost factors vs. select other hard rock lithium regions

Piedmont Lithium Limited (“Piedmont” or “Company”) is pleased to provide an update on the development of the Company’s 100% owned Piedmont Lithium Project (“Project”) in the Carolina Tin-Spodumene Belt (“TSB“) in North Carolina, United States. The Company remains on schedule to release a maiden Mineral Resource estimate in accordance with the JORC Code by the end of the 2nd Quarter 2018 and the integrated Scoping Study shortly thereafter.

Keith D. Phillips, President and Chief Executive Officer, said, “The progress made over the past several months with land acquisition, drilling and metallurgical test work reinforces our view that the Piedmont Lithium Project will develop into a world class, low cost, integrated lithium operation, as formerly existed in North Carolina. The Company aims to develop the project on a phased approach using conventional technology, much of which was initially developed in our home region.”

For further information, contact:

Keith D. Phillips               

Anastasios (Taso) Arima

President & CEO                        

Executive Director

T: +1 973 809 0505                   

T: +1 347 899 1522

E: kphillips@piedmontlithium.com   

E: tarima@piedmontlithium.com

 

 

 

 

Cision View original content:http://www.prnewswire.com/news-releases/piedmont-announces-positive-initial-metallurgical-results-and-sets-development-timeline-300626257.html

SOURCE Piedmont Lithium Limited


Further High Grade Lithium Mineralisation Identified During Resource Drilling In North Carolina

NEW YORK, April 3, 2018 /PRNewswire/ —

  • Piedmont has received further high-grade assay results from a further 21 holes with all holes showing high grade mineralisation including:
    • 20.6m of cumulative thickness of mineralization (non-continuous) across 4 pegmatites which includes high grade intercepts of 14.6m @ 1.21% Li2O, 2.5m @ 1.38% Li2O and1.8m @1.37 Li2O in Hole 17-BD-160
    • 26.5m of cumulative thickness of mineralization (non-continuous) across 7 pegmatites which includes high grade intercepts of 6.0m @ 1.44% Li2O, 1.5m @ 2.15% Li2O and2.3m @1.16 Li2O in Hole 17-BD-162
    • 20.5m of cumulative thickness of mineralization (non-continuous) across 4 pegmatites which includes high grade intercepts of 10.0m @ 1.19% Li2O, 2.0m @ 1.53% Li2O and5.1m @1.22 Li2O in Hole 17-BD-144
    • 18.1m of cumulative thickness of mineralization (non-continuous) across 5 pegmatites which includes high grade intercepts of 8.1m @ 1.68% Li2O, 2.9m @ 1.40% Li2O and1.5m @1.32 Li2O in Hole 17-BD-151
  • Infill drilling is nearing completion and the Company is now looking forward to moving drill rigs to high priority exploration targets on its properties
  • Maiden resource continues to remain on-track for delivery by end of 2nd Quarter 2018

Piedmont Lithium Project Drill Location Figure Map

Piedmont Lithium Limited (“Piedmont” or “Company”) is pleased to advise that the Company has received assay results from a further 21 holes from the current 20,000 meter drilling campaign on its properties in the Carolina Tin-Spodumene Belt (“TSB“) in North Carolina, United States. The Company remains on schedule to release a maiden Mineral Resource estimate in accordance with the JORC Code by the end of the 2nd Quarter 2018.

The results build upon the previous drilling completed on the property and continue to show similar high-grade mineralisation and pegmatite intercepts. The Company has six drill rigs on site and has completed 76 holes totalling just over 13,000 meters of its planned 20,000-meter Phase 3 program. Infill drilling is expected to be completed within the next few weeks and upon completion the Company will move to drilling high priority targets to assist in delineating further potential resources.  

Keith D. Phillips, President and Chief Executive Officer, said, “Infill drilling is going very well and resource modelling is ongoing.  We look forward to completing the infill work soon and then shifting to exploration drilling, leading ultimately to a maiden Mineral Resource estimate in June and a Scoping Study shortly thereafter.”

For further information, contact:

Keith D. Phillips

Anastasios (Taso) Arima

President & CEO

Executive Director

T: +1 973 809 0505

T: +1 347 899 1522

E: kphillips@piedmontlithium.com

E: tarima@piedmontlithium.com

Phase 2 Results and Discussion

The current Phase 3 drilling campaign is focused on infill drilling along the trends defined by the Phase 2 program. These 21 holes (holes 144 to 165, awaiting assays on hole 155) are part of the initial infill drilling required for the compilation of the maiden Mineral Resource estimate. These results (Appendix 1) are consistent with Phase 2 results and are currently being added to the geological model.

Approximately 13,000 meters of the 20,000-meter Phase 3 drilling program will be focused on infill drilling whereas the remaining meterage will test high priority exploration targets on the property, test the along strike and down dip extensions within the current drilling area, and test the potential of the newly acquired properties.  To date, 73 infill holes totalling just over 12,500 meters have been completed whereas 3 exploration holes for approximately 500 meters have been completed. The Company expects the completion of the infill drilling campaign in the coming weeks with emphasis switching to the exploration and wide spaced drilling portion of the Phase 3 program

About Piedmont Lithium

Piedmont Lithium Limited (ASX: PLL; OTC-Nasdaq Intl: PLLLY) holds a 100% interest in the Piedmont Lithium Project (“Project”) located within the world-class Carolina Tin-Spodumene Belt (“TSB”) and along trend to the Hallman Beam and Kings Mountain mines, historically providing most of the western world’s lithium between the 1950s and the 1990s.  The TSB has been described as one of the largest lithium provinces in the world and is located approximately 25 miles west of Charlotte, North Carolina.  It is a premier location to be developing and integrated lithium business based on its favourable geology, proven metallurgy and easy access to infrastructure, power, R&D centres for lithium and battery storage, major high-tech population centres and downstream lithium processing facilities.

The Project was originally explored by Lithium Corporation of America which eventually was acquired by FMC Corporation (“FMC”). FMC and Albemarle Corporation (“Albemarle“) both historically mined the lithium bearing spodumene pegmatites within the TSB and developed and continue to operate the two world-class lithium processing facilities in the region which were the first modern spodumene processing facilities in the western world. The Company is in a unique position to leverage its position as a first mover in restarting exploration in this historic lithium producing region with the aim of developing a strategic, U.S. domestic source of lithium to supply the increasing electric vehicle and battery storage markets.

Piedmont, through its 100% owned U.S. subsidiary, Piedmont Lithium Inc., has entered into exclusive option agreements and land acquisition agreements with local landowners, which upon exercise, allow the Company to purchase (or in some cases long-term lease) approximately 1,200 acres of surface property and the associated mineral rights.

Forward Looking Statements

This announcement may include forward-looking statements. These forward-looking statements are based on Piedmont’s expectations and beliefs concerning future events. Forward looking statements are necessarily subject to risks, uncertainties and other factors, many of which are outside the control of Piedmont, which could cause actual results to differ materially from such statements. Piedmont makes no undertaking to subsequently update or revise the forward-looking statements made in this announcement, to reflect the circumstances or events after the date of that announcement.

Competent Persons Statement

The information in this announcement that relates to Exploration Results is based on, and fairly represents, information compiled or reviewed by Mr. Lamont Leatherman, a Competent Person who is a Registered Member of the ‘Society for Mining, Metallurgy and Exploration’, a ‘Recognized Professional Organization’ (RPO). Mr. Leatherman is a consultant to the Company. Mr. Leatherman has sufficient experience that is relevant to the style of mineralization and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr. Leatherman consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

 

Piedmont Lithium Project Long Section

Piedmont Lithium Project Cross Section

Cision View original content with multimedia:http://www.prnewswire.com/news-releases/further-high-grade-lithium-mineralisation-identified-during-resource-drilling-in-north-carolina-300624019.html

SOURCE Piedmont Lithium Limited